Heat-pump source and price threshold checker
Define the service boundary, then check every constraint. Built-in values are resettable fictional teaching examples; results prepare further review.
Heat and duration must be positive, 1 < COP ≤ 10, and 0 < boiler efficiency ≤ 100%. Limits, source availability and losses may be zero. Signed energy prices are preserved.
Methods, formulas and boundaries
Simplified steady heating balance: gross heat-pump heat = useful process heat + entered downstream heat loss; compressor work = gross heat / entered heating COP; required source heat = gross heat − compressor work.
COP applies to gross heat-pump output divided by compressor electricity at the stated operating point; require 1 < COP ≤ 10 here. List auxiliaries separately and avoid counting the same auxiliary twice. Useful delivery COP = useful heat/(compressor + listed auxiliaries).
For the same useful service and compatible LHV/HHV basis, boiler fuel = useful heat/boiler efficiency. Energy-only break-even electricity price = boiler period fuel cost / total heat-pump period electricity.
The price threshold and hypothetical cost remain visible when a physical gate fails. They do not establish savings, annual performance, payback, carbon reduction or an approved design. Include tariffs, capital, maintenance and downtime in a separate project study.
Source and delivery temperatures, flow, part-load behaviour and source timing require a validated performance map. This screen does not infer a COP from temperature, simulate a changing source, or validate pressure, steam quality or protection.
Continue learning and project preparation
Study the related lessonReviewed 26 October 2026. Teaching methods and calculations are original. Primary references support background; they are not local project approvals.
DOE · Industrial Heat Pumps for Steam and Fuel SavingsSources and review date
Reviewed 26 October 2026. Text, diagrams and exercises are original. All numerical cases use stated teaching assumptions, rather than site measurements or manufacturer commitments. These primary sources support the technical background; verify their applicability to each project.
[H1] ARENA / HILT CRC · TES for Industrial Process Heat: A Practical Guide (2026) ↗
Integrated assessment of process heat and thermal storage.
[H2] IEA · How a Heat Pump Works ↗
Heat-source, useful-output and COP concepts.
[H3] IEA · Heat Pump Monitor 2026: Key Findings ↗
Industrial integration, temperature and economic context.
[H4] DOE · Industrial Heat Pumps for Steam and Fuel Savings ↗
Foundational engineering explanation; not a current local approval rule.