ES1.1 · Storage services and technology selection

A storage project buys a time-dependent service, rather than an inventory alone. Specify the net power at a named meter, uninterrupted duration, response delay, recovery window and protected reserve. Heating, cooling and electrical backup are different services even when all quantities are expressed in MWh.

Learning objectives

  • Calculate the event energy.
  • Identify the first failed constraint for each device.
  • Specify the next evidence request.

Allow 30–45 minutes including derivations and exercises. All numerical values are teaching assumptions.

1. Define the delivered service

A storage project buys a time-dependent service, rather than an inventory alone. Specify the net power at a named meter, uninterrupted duration, response delay, recovery window and protected reserve. Heating, cooling and electrical backup are different services even when all quantities are expressed in MWh.

2. Follow the conversion chain

Batteries store electrochemical energy; pumped hydro stores elevated water; flywheels store motion. Air storage depends on pressure, temperature and a thermodynamic cycle. Hydrogen and thermal routes require explicit final conversion stages if electricity is the contracted output. Each stage has power and availability limits.

Lesson service and evidence flow

Source energyStorage stateConversionNet service
Original learning diagram. Arrows describe the service or evidence sequence; different energy media cannot be added directly.

3. Separate energy from power

For constant duty, E=P×t. For varying duty, sum power multiplied by each interval length. Available capacity must be stated at the output boundary after losses and reserve deductions. Passing the energy check does not establish adequate converter current, startup behaviour or voltage support.

4. Screen local constraints first

Hydro needs usable elevation, water and civil works; air storage needs a suitable pressure system and heat balance. Thermal storage needs a compatible temperature service. A battery still needs thermal management, protection and permission. Technology rankings should follow these gates rather than a generic cost-per-kWh chart.

5. Prepare the decision record

Record why each option passes, fails or remains unknown. Keep source dates and operating conditions beside every assumption. When data are absent, create a measurement or supplier evidence action with an owner. Do not turn an assumed retention rate or response time into an equipment guarantee.

Case and independent exercises

Fictional duty: 2 MW net for 20 seconds, repeated every ten minutes. Device A provides 3 MW but only 0.008 MWh usable AC. Device B provides 1 MW and 1 MWh. No transfer-time or recovery evidence is available.

  1. Calculate the event energy.
  2. Identify the first failed constraint for each device.
  3. Specify the next evidence request.

Worked answers and reasoning

Attempt the exercises before opening each answer.

Answer 1

2×20/3600 = 0.011111 MWh, or 11.111 kWh at the net service boundary. The short duration reduces energy, but not the 2 MW power requirement.

Answer 2

A fails energy: 0.008 < 0.011111 MWh. B fails power: 1 < 2 MW. Neither can be selected merely because one nameplate number is larger.

Answer 3

Request event waveform, transfer/response behaviour, usable energy at operating conditions and recovery before the next event. Repetition creates a recharge constraint independent of the first discharge.

Decision method to take away

Record why each option passes, fails or remains unknown. Keep source dates and operating conditions beside every assumption. When data are absent, create a measurement or supplier evidence action with an owner. Do not turn an assumed retention rate or response time into an equipment guarantee.

Sources and review date

Reviewed 26 October 2026. Text, diagrams and exercises are original. All numerical cases use stated teaching assumptions, rather than site measurements or manufacturer commitments. These primary sources support the technical background; verify their applicability to each project.

[S1] DOE FEMP · BESS Procurement Checklist ↗
Early procurement questions and scope.

[S2] DOE FEMP · Lithium-ion BESS Technical Specifications ↗
Customisable procurement template, not a local approval.